Home buyers can have all option to get relief
( Experion Developers
Pvt. Ltd. Versus Sushma Ashok Shiroor )
SC in a recent case decided on
07.04.2022 takes a very liberal view in favour of home buyers who invested
their hard earned money in developers project but does not get possession
within stipulated time
Case Experion Developers Pvt.
Ltd. Versus Sushma Ashok Shiroor ;Civil Appeal No. 6044 of 2019 With Civil Appeal
No. 7149 of 2019 Decided on April 07,
2022
Bench ;Uday Umesh Lalit; J, S.
Ravindra Bhat; J, Pamidighantam Sri Narasimha; J
No new theory evolved in this
case but made it clear that commission has the power to give relief what the
home buyer choses. Home buyer is free to make any prayer and commission may
grant the same if merits so permit
SC has allowed three fold
choices to the home buyer who has not been given possession of dwelling
within stipulated time frame
Dr
Prem Lata ,Legal Head VOICE
SC has allowed three fold
choices to the home buyer who has not been given possession of dwelling
within stipulated time frame
1. The power to direct refund of
the amount and to compensate a consumer for the deficiency in not delivering
the apartment as per the terms of Agreement is within the jurisdiction of the
Consumer Courts A consumer can
pray for refund of the money with interest and compensation
2. The consumer could also ask for possession of
the apartment with compensation.
3. The consumer can also make a
prayer for both in the alternative. If a
consumer prays for refund of the amount, without an alternative prayer, the
Commission will recognize such a right and grant
“The freedom to choose the
necessary relief is of the Consumer and it is the duty of the Courts to honour
it.”
The above order makes the
position clear that home buyer can be given compensation in all the situations
whether asks for refund with interest& compensation or possession with delayed compensation
Objection raised by builder
The objection raised by developer
was that
·
Consumer
is entitled for delayed compensation only and since occupation certificate has
been applied and shall be obtaining ,he is entiled for compensation for delay
to the tune of Rs Rs. 4,54,052/-.
·
42
months period expires on 26-6-2016, “the trigger date for clause 10.1 is
26.12.2012, which is the date of execution of the apartment buyer’s agreement”.
The Commission calculated 42 months from this period, which turns out to be
26.06.2016. Further, adding the grace period of 180 days, the time for delivery
would expire on 26.12.2016.
·
Occupation
Certificate for Phase-I of the project had already been obtained on 06.12.2017,
and application for Occupation Certificate for Phase-2, had already been made.
In the affidavit of evidence, the Developer contended that it secured the
Occupation Certificate on 23.07.2018 and a notice of 3 possession was issued to
the Consumer on 24.07.2018. It was claimed that since possession can be handed
over, the complaint must be dismissed
NC Orders
The Commission, in its judgment
dated 19.06.2019, allowed the complaint after referring to Clause 10 (relating
to the project completion period), Clause 11 (relating to the possession and
conveyance of the apartment), as well as Clause 13 (relating to delay in
possession). The Commission found that the agreement is one-sided, heavily
loaded against the allottee and entirely in favour of the Developers. Following
the decisions of this Court in Pioneer Urban Land and Infrastructure Ltd. v.
Govind Raghvan,5 (“Pioneer”), the Commission directed the Developer to refund the
amount of Rs.2,36,15,726/- with interest @ 9% p.a. following Pioneer Urban Land and Infrastructure Ltd. v.
Govindan Raghvan (2019) 5 SCC 725
Both the parties filed appeals
against the above order by NC
·
The
Developer filed the present Civil Appeal No. 6044/2019. against these findings of
payind refund with interst when possession is offered and the consequential directions of the
Commission
·
The
Consumer also filed an appeal being Civil Appeal No. 7149/2019, challenging the
Commission's judgment to a limited extent for grant of an enhanced interest @
24% p.a
Objections raised against this
order before SC by Developers
·
The
decision of this Court in Pioneer has no application to the facts of the
present case, as in Pioneer, the Court did not have to deal with Delay
Compensation Clause like in the present case.
·
Terms
of the Apartment Buyer’s Agreement alone would govern the relations between the
parties. No prejudice would be caused to the Consumer if he is asked to take
possession of the property.
·
Referring
to the provisions of the Real Estate (Regulation and Development) Act, 20166
and particularly to the Regulations made by Haryana Real Estate Regulatory
Authority, which were relied on in Pioneer case, Builder submitted that the
Consumer has elected to proceed under the Consumer Protection Act, 1986 and
therefore the provisions of RERA Act will not apply and the Pioneer cannot be
followed as a precedent.
·
The
interest granted by the Commission is excessive in both the period of the grant
and the rate of interest.
Three issues before the SC
I. Whether
the Commission has the power under the Consumer Protection Act, 1986 to direct
refund of the amount deposited by the Consumer with interest when developer
ready to give possession
II. Whether
the terms of the Apartment Buyers Agreement amount to an ‘unfair trade
practice’ and
III. Whether
Commission is justified in referring Pioneer Case which was mainly decided
under on RERA Act
HELD;
A) Order for interest justified (Issue -1)
Referred cases
In
LDA v. M.K. Gupta,
this Court held that when a person hires the services of a builder, or a
contractor, for the construction of a house or a flat, and the same is for a
consideration, it is a “service” as defined by Section 2(o) of the Consumer
Protection Act, 1986. The inordinate delay in handing over possession of the
flat clearly amounts to deficiency of service.
In Fortune Infrastructure v. Trevor D’Lima,
this Court held that a person cannot be made to wait indefinitely for
possession of the flat allotted to him, and is entitled to seek refund of the
amount paid by him, along with compensation. The respondent flat purchaser has
made out a clear case of deficiency of service on the part of the appellant
builder. The respondent flat purchaser was justified in terminating the
apartment buyer’s agreement by filing the consumer complaint, and cannot be
compelled to accept the possession whenever it is offered by the builder. The
respondent purchaser was legally entitled to seek refund of the money deposited
by him along with appropriate compensation.
B)Unfair contract clause to be
struck down (Issue -2)
“In
term of a contract will not be final and binding if it is shown that the flat
purchasers had no option but to sign on the dotted line, on a contract framed
by the builder. The contractual terms of the agreement dated 8-5-2012 are ex
facie one sided, unfair and unreasonable. The incorporation of such one-sided
clauses in an agreement constitutes an unfair trade practice as per Section
2(r) of the Consumer Protection Act, 1986 since it adopts unfair methods or
practices for the purpose of selling the flats by the builder.”
“In view of the above discussion, we have no hesitation in holding that the terms of the apartment buyer’s agreement dated 8-5-2012 were wholly one-sided and unfair to the respondent flat purchaser. The appellant builder could not seek to bind the respondent with such one-sided contractual terms.”
Referred cases
Wing
Commander Arifur Rahman Khan and Aleya Sultana & Ors. v. DLF Southern Homes
Private Limited (2020) 16 SCC 512
SC
held that there
is no embargo on the award of compensation beyond the rate stipulated in the
Apartment Buyer’s Agreement where handing over the possession of the flat has
been delayed. The Court observed that the Consumer Forums must take a robust
and a common-sense approach by taking judicial notice of the fact that flat
purchasers obtained loans and are required to pay EMIs to financial
institutions for subserving their debts. The Delay Compensation Clause provided
for Rs. 5 per square foot per month. is clearly one-sided and does not maintain
a level platform or even reflect a bargain between the parties. The Court
granted additional compensation @ 6% p.a. simple interest to each buyer
therein, over and above the Delay Compensation Clause.
DLF Home Developers Ltd. v. Capital Greens Flat Buyers9. 8 NBCC (India) Ltd. v. Shri Ram Trivedi (2021) 5 SCC 273 9 DLF Home Developers Ltd. v. Capital Greens Flat Buyers Association & Ors. (2021) 5 SCC 537
“the compensation could be granted even if possession had been delivered.”
IREO
Grace Realtech (P) Ltd. V. Abhishek Khanna & Ors. (2021) 3 SCC 241
A three-judge bench of this Court in noticed
the delay compensation clause, which is similar to the clause in the present
case, which provided that the Developer would be liable to pay delay
compensation @ Rs 7.5 per square foot which works out to approximately 0.9 to
1% p.a. The Court held that this Clause is one-sided and entirely loaded in
favour of the Developer and against the allottee. The Court concluded that the
powers of the Consumer Court were in no manner constrained to declare a
contractual term as unfair and one-sided as an incident of the power to
discontinue unfair or restrictive trade practices.
Poineer Case well applicable (Issue
-3)
·
Real
Estate (Regulation and Development) Act, 2016 - Consumer Protection Act and the
RERA Act neither exclude nor contradict each other - They are concurrent
remedies operating independently and without primacy. [Referred to Imperia
Structures Ltd v. Anil Patni (2020) 10 SCC 783 and IREO Grace Realtech (P) Ltd.
V. Abhishek Khanna (2021) 3 SCC 241] (Para 14.1)Hence applicability of Pioneer
case is not out of place
·
Remedies
available under the provisions of the CP Act are additional remedies over and
above the other remedies including those made available under any special
statutes; and that the availability of an alternate remedy is no bar in entertaining
a complaint under the CP Act.
·
In
terms of Section 18 of the RERA Act, if a promoter fails to complete or is
unable to give possession of an apartment duly completed by the date specified
in the agreement, the promoter would be liable, on demand, to return the amount
received by him in respect of that apartment if the allottee wishes to withdraw
from the Project. Such right of an allottee is specifically made “without
prejudice to any other remedy available to him”. The right so given to the
allottee is unqualified and if availed, the money deposited by the allottee has
to be refunded with interest at such rate as may be prescribed. The proviso to
Section 18(1) contemplates a situation where the allottee does not intend to
withdraw from the Project. In that case he is entitled to and must be paid
interest for every month of delay till the handing over of the possession. It
is up to the allottee to proceed either under Section 18(1) or under proviso to
Section 18(1). The case of Himanshu Giri came under the latter category. The
RERA Act thus definitely provides a remedy to an allottee who wishes to
withdraw from the Project or claim return on his investment. 26. It is,
therefore, required to be considered whether the remedy so provided und
· Interpretation of Statutes - When Statutes provide more than one judicial fora for effectuating a right or to enforce a duty-obligation, it is a feature of remedial choices offered by the State for an effective access to justice. Therefore, while interpreting statutes provisioning plurality of remedies, it is necessary for Courts to harmonise the provisions in a constructive manner
Consumer appeal prayed that: (i) the payment of interest
must be from the date of payment of each instalment and (ii) the rate of interest
must be 24% p.a.
Court Held-
DLF Homes Panchkula Pvt Ltd v. DS
Dhanda and in modification of the direction issued by the Commission, we direct
that the interest on the refund shall be payable from the dates of deposit. At
the same time, we are of the opinion that the interest of 9 per cent granted by
the Commission is fair and just and we find no reason to interfere in the
appeal filed by the Consumer for enhancement of interest.
Above is the most balanced
judgment ,well defined and with all
justifications giving opportunity to be heard to both the parties with the same
ration . This is more important for the reason it defines with total clarity as
to what relief Home buyer is entitled to in case of developer defaulting in
giving possession in time
By Dr Prem Lata
Become a Member of the new revolution "Consumer Awakening" and instantly expand your knowledge with the Important Landmark Judgements, Laws Laid down by the Supreme Court for Consumer Rights, Get access to hundreds of Featured Articles in 2 different Languages; English and Hindi - a valuable professional resource to draw upon, and a powerful, collective voice to advocate for your protection of rights as a consumer nationwide.
Thank you for your interest in becoming a "Consumer Awakening" Member!
You will find information on Customer Rights, what we're doing and how to become a member. If you are looking forward to become a member of our portal and gain access to Hundreds of Featured Articles which will clearly give you an insight of yoru rights as a Consumer, then Read Further. more detail on our technologies and technology process,