WHEN A
MONEY DEMAND BY THE BUILDER IS INVALID
(Not depositing money is not violation of
terms and conditions)
A consumer often meets with a situation
wherein builder issues demand letter as per the agreed terms. He also expects
interest in case consumer fails to deposit the money as per agreed payment
schedule. Reminder letters are also issued to the customer /purchaser with
fresh demand amount which includes interest also. There is a warning also
referring to agreement clause by which builder reserves the right to cancel the
booking and forfeit the booking amount too.
On the other hand there is all possibility of
delay in construction and builder had offered a very low /minimum penalty for
his default .Since purchaser does not have equal bargaining power with the builder,
hence he signs the agreement.
Consumer is in a fix-builder is
unapproachable to listen that construction is not up to the mark and he does
not want to pay as per agreed schedule time. If he defaults and waits for his
correspondence to reach to some logical resolution, the interest accrues to
leaps and bounds and ultimately consumer has to either pay everything or stands
on the verge of risk of getting booking cancelled.
Here is a case decided by hon’ble National
Commission where in has been clarified that money demand made by the builder
can be termed as invalid demand if construction has not started.
In a case of Vinod Kumar Kochar v/s Earh
Infrastructure Ltd &others 1(2016) CPJ 183 (NC) decided on 7.9.2015 in
complaint case no 174 of 2014. ,one Shri Vinod Kumar Kochara and his wife
Karuna Kochar were allotted a residential unit no. 103,Vayu tower,group
housing complex known as Earth Towne at plot no GH-04,Sector-1 ,Greater
Noida UP vide allotment letter dated 17.6.2011.The cost of apartment was fixed
at Rs 3392550/-and after other charges added up to the tune of Rs 533625/- the
total cost of apartment comes to Rs 3926175/-.Complainant paid Rs 10,83,945/-
towards part payment .
OP never sent any demand letter for the
balance amount, neither there was any work done except for digging work done on
the site. Builder cancelled the allotment and forfeited the earnest money
alleging non payment of money as scheduled.
It stands admitted by the builder that no
work was done in respect of the project in question .Complainant could also
establish that he never received any demand letter even. National commission
held-
‘Although the complainants were bound to pay
the amount as per time shedule, yet they must be made aware and demand notice
was to be sent informing them the status of construction. When OP’s have not
started work how could they send demand letter. Consequently the cancellation
of flat made by OP’s is illegal and invalid. OP must prove that in spite of
work done and demand notice sent, complainant has failed to pay. They are
entitled to cancel allotment only after that Court went ahead directing
OP’s to give interest on the amount already paid to the tune of Rs 1083945/-
with 9% interest from the judgment month i.e. Jan 2015 till possession is
given.
It stands a landmark order in favour of
consumers when builder threats to the customers for cancellation of unit and
forces him to go on making payment in spite of the fact no work done.
However every case has its own facts and
circumstances and finding of the courts vary in every different circumstance. In the
case of Devender Kumar v/s U.P.Awas Vikas Parishad 1(2006) CPJ 188(NC) in
revision petition no 3277/2014 decided on 26.5.2014, the order was against the
consumer finding him clear defaulter and cancellation of flat was held
justified. Complainant had paid registration amount of Rs 5000/- and got
allotment on 11.3.1992.He was to pay Rs11, 637/-and Rs 8769 in lump sum and
balance money was to be paid in 144 monthly installments of Rs1567/-. Complainant
never paid monthly installments .He was sent notice under registered post dated
23.11.1995 which was duly received as per record but remained unanswered. Another
letter dated6.9.1996 for cancelling the flat was sent followed by yet another
letter of cancellation dated 21.8.1997. Now complainant files complaint with
prayer for various prayers in the year 2003, when dismissed for want of jurisdiction,
files another complaint in the year 2005 on the same issue before the
appropriate case with application for condo nation of delay. The case was
defeated on merit and court held cancellation very much valid having all
proofs on record against complainant.
………………………………………………………………………………
Become a Member of the new revolution "Consumer Awakening" and instantly expand your knowledge with the Important Landmark Judgements, Laws Laid down by the Supreme Court for Consumer Rights, Get access to hundreds of Featured Articles in 2 different Languages; English and Hindi - a valuable professional resource to draw upon, and a powerful, collective voice to advocate for your protection of rights as a consumer nationwide.
Thank you for your interest in becoming a "Consumer Awakening" Member!
You will find information on Customer Rights, what we're doing and how to become a member. If you are looking forward to become a member of our portal and gain access to Hundreds of Featured Articles which will clearly give you an insight of yoru rights as a Consumer, then Read Further. more detail on our technologies and technology process,